Job Reports > Vibro Hammers

Cronulla
New South Wales

Sea wall remediation.

The project presents a number of significant project management challenges including difficult site access, public access management, environmental impacts from storms / tidal activity and onstantly shifting sands.

Mayfield (Newcastle)
New South Wales

Construction of a new seawall to replace old one

Steelcom has recently supplied Emanon the Müller Excavator Mounted Vibrator (MS-7 HFBS) for application on its current BHP Remediation project in Mayfield (Newcastle) NSW.

Wollongong
New South Wales

Port Kembla Berth 6 wharf construction

Steelcom have introduced the largest vibro-driver currently available in Australia to the Port Kembla development project.

Coffs Harbour
Northern New South Wales

Deep sea release, cofferdam construction

Barclay Mowlem Candac used two PTC vibratory hammers throughout this project – their own 25H2 and Steelcom's new 30H1.

Groote Eylandt
600km east of Darwin

Barge wharf extension

Sheet pile was the major construction material. Contractor used standard frequency PTC 30HI hammer with vibratory power of 193kw to drive over 90 LX25 sheet piles 11.8m in length supplied ex stock by Steelcom.

Raymond Terrace
New South Wales

Abutment Reinforcement

Contractor Civilbuild is seen here using our 15HF3 to drive 8 metre LX16 sheet pile into stiff clay for an abutment reinforcement.

Newcastle
New South Wales

Ferry Wharf Construction

Contractor Newcastle Wharf and Jetty Repairs used our 50HL hammer to drive 21.7 metre long steel tubes that were 900mm diameter with a wall thickness of 16mm.

Auckland
New Zealand

Wharf Construction

Fletcher Construction used Steelcom's 50HL hammer in the construction of wharves at Marsden Point, 150km north of Auckland.

Cantebury
New Zealand

Foundation Construction

For this ICT project, pile foundation columns were created and the PTC30H1 Vibro Hammer was used to drive 900mm dia casing down 15m.

 


  Privacy Policy | Sitemap